Sunday, 6 September 2015

Week 42: 'getting there'...slowly but surely

Scaffolding down now
Finishing touches to joinery finishes

Light fittings installed

Sunday, 23 August 2015

Week 40: 3 weeks to go


The finishing details around the windows
Joe checks out the drainpipes

Flooring installed in the lounge


Kitchen delivered for installation

Sunday, 9 August 2015

Week 38: 5 weeks to go...

First fit complete in family bathroom
More detailing on the staircase
A 'mess' of underfloor heating pipes



The bath arrives

Sunday, 26 July 2015

Week 36: Only 7 weeks to go....

Nice to see the sunlight in the hall
The staircase is almost fully formed now

The 'Stolit K' render has now been applied

The underfloor heating system is being installed currently
Boiler installed in the Utility Room



Friday, 17 July 2015

Week 35: Rendering, Painting & Staircase "8 weeks to go!"

The basecoat for the Sto render is applied



"Twin exhausts" fitted to the gutters!



The beginnings of the staircase....
...and the beginning of the end of the ladder!
a very neat job!
Painting and decorating is underway now too.




Saturday, 11 July 2015

Week 34: Plastering underway


The plasterers start to put 'the icing on the cake' in Joe's room
Hallway gets a skimming too!

'Fuel for builders'

Week 33: Services Install Commenced

Trench dug for services

Prep work for kitchen nears completion


The supervisors check progress on site