Sunday, 6 September 2015
Week 42: 'getting there'...slowly but surely
Scaffolding down now
Finishing touches to joinery finishes
Light fittings installed
Sunday, 23 August 2015
Week 40: 3 weeks to go
The finishing details around the windows
Joe checks out the drainpipes
Flooring installed in the lounge
Kitchen delivered for installation
Sunday, 9 August 2015
Week 38: 5 weeks to go...
First fit complete in family bathroom
More detailing on the staircase
A 'mess' of underfloor heating pipes
The bath arrives
Sunday, 26 July 2015
Week 36: Only 7 weeks to go....
Nice to see the sunlight in the hall
The staircase is almost fully formed now
The 'Stolit K' render has now been applied
The underfloor heating system is being installed currently
Boiler installed in the Utility Room
Friday, 17 July 2015
Week 35: Rendering, Painting & Staircase "8 weeks to go!"
The basecoat for the Sto render is applied
"Twin exhausts" fitted to the gutters!
The beginnings of the staircase....
...and the beginning of the end of the ladder!
a very neat job!
Painting and decorating is underway now too.
Saturday, 11 July 2015
Week 34: Plastering underway
The plasterers start to put 'the icing on the cake' in Joe's room
Hallway gets a skimming too!
'Fuel for builders'
Week 33: Services Install Commenced
Trench dug for services
Prep work for kitchen nears completion
The supervisors check progress on site